Just a reminder to everyone that Marshfield's Special Town Meeting will take place on Monday, October 24th. The meeting will begin at 7:00 PM and will take place in the MHS Auditorium.
The MPSD will have two articles in relation to the Furnace Brook Middle School. One article will seek $700,000 to replace the three existing boilers at the FBMS with new, high efficiency boilers.
In addition, there will be an article seeking $60,000 to pay for a Schematic Design Study at the FBMS for a potential roof replacement project. The district is seeking reimbursement from the Massachusetts School Building Authority (MSBA) to assist with the cost of this potential project.